Paving Main

The Main Street & Market Street intersection is now open! Over the past couple of weeks, crews have worked to reopen the roadways to vehicles. A big milestone of the project has occurred the with precast concrete seat walls being delivered and installed. Topsoil has also been placed in the planter curbs on the east end of the project.



Current Schedule

As paving and landscaping of the Ratingen Platz continue to progress, more demolition will occur on Market and Prospect. We have been working with the Ribs, Rods, and Rock 'N Roll committee members to ensure that this area completed by the first week of September. There will be a lot of finishing touches to occur as the planters are backfilled with topsoil, as well as the installation of bike racks, metal benches, garbage & recycling bins, and crash bollards.